Manual
Table Of Contents
- 1. Description
- 2. System Requirements
- 3. OPC Requirements
- 4. Valve Manager Application
- 4.1. Installation
- 4.2. Running the Valve Manager application
- 4.3. Creating a Data Source
- 4.4. Creating a Project
- 4.5. Working with Multiple Projects
- 4.6. Editing a Project
- 4.7. Removing a Project
- 4.8. Adding, Removing, and Renaming Valves
- 4.9. Configuring a Valve Profile
- 4.10. Applying the Same Profile to Multiple Valves
- 4.11. Initiating a Test
- 4.12. Recording Automated Tests and External Events
- 4.13. Clearing Valve Test History
- 4.14. Controlling the Monitor
- 4.15. Project Tree
- 4.16. Main Window

Trusted
TM
Valve Manager T8031
Issue 2 Oct 05 PD-T8031 34
4.7. Removing a Project
A project can be removed from the Valve Manager’s configuration by selecting “Project | Delete
Project” from the main menu. Before the project is deleted, the Valve Manager will display a dialog box
asking for confirmation.
Figure 31 Deleting a Project
Selecting “Yes” will bring up another dialog box asking if you want to remove the project’s tables from
the database. Selecting “Yes” will remove all tables associated with the project. Selecting “No” will
retain the tables in the database.
Figure 32 Deleting Database Tables