Chapter 12 Demand Control
2. Enter your configured password.
3. Configure the demand control schedule, kW setpoint,
and billing end date.
For the Efficient Industries example, the demand control
is on from 8:00 to 18:00, Monday through Friday.
4. Click on the load config button to configure the
individual loads.
For the efficient industries example, loads are configured
as follows:
Load Description Priority Rated KW On Delay SEC Off Delay SEC Max Off Time
SEC
1 Air Compressor 1 1 21 60 60 900
2 Air Compressor 2 1 21 60 60 900
3 AHU 1 Production 4 15 120 120 1800
4 AHU 2 Production 4 15 120 120 1800
5 AHU 3 Shipping 5 12 120 120 1800
6 AHU 4 Office 7 10 120 120 1800
7 Exhaust Fan 1 2 2 30 30 2700
8 Exhaust Fan 2 2 2 30 30 2700
9 Exhaust Fan 3 10 2 30 30 2700
10 Exhaust Fan 4 10 2 30 30 2700
11 Lighting Production 3 6 15 15 1200
12 Lighting Production 6 6 15 15 1200
13 Lighting Shipping 8 6 15 15 3600
14 Lighting Office 9 6 15 15 3600