t Owner manual
Rockwell Automation Publication IASIMP-QS016C-EN-P - October 2014 151
FactoryTalk EnergyMetrix Software Meter and Tag Setup Chapter 7
11. Confirm the meter was created in the correct
group.
For the Efficient Industries Plant 1
example,
the electric meter listing should look like this.
Assign Meter Tags to OPC Device
You will now assign meter tags to an OPC server.
For the Efficient Industries Plant 1
example, you will assign only the Real Energy Net meter tag to the Data Center (OPC
Server) for logging consumption.
1. Select the meter.
For this example, select Data Center (OPC Server).
2. Click the Meter Setup tab.
3. Click the Add a new meter tag link
.