Key Steps to Commissioning a PF7000 Drive
As a guide for a commissioning engineer, the major steps involved in the commissioning of medium
voltage PF7000 drives are outlined below in a sequential order. For detailed instructions, always refer
to PowerFlex7000 User Manual.
Review the drawings and identify all sources of energy that apply to the drive system and get
better understanding of the application to which the drive system is applied.
Follow Safety Procedures and apply LOTO before working on the equipment
Complete all Power Off checks and note down motor and drive nameplate data
Apply control power and perform Power On checks
Perform Gating Test
Program the drive after verifying the information on EDs and DDs against the equipment
nameplate data.
Perform System Test and verify operation of the drive and the associated controls
Remove any jumpers used during system test
Inspect the drive line-up and ensure that no tools are left inside the cabinets before closing them.
Apply medium voltage and complete incoming line phasing checks and take harmonic
measurements
Perform DC Test. Ensure that the Diagnostic Trend is setup and ready before attempting the DC
Test.
Perform Stationary Autotune tests (first 2 autotune tests)
Bump the motor for rotation check
Complete Rotating Autotune tests (last autotune test)
Save the parameters in NVRAM and also transfer them from Drive to Memory and also print the
Drive Setup to your laptop
Start the drive in normal operation, print variables and capture waveforms
Complete commissioning documentation