Rockwell Automation Publication 23C-IN001B-EN-P - June 2013 187
Electrical Installation Chapter 4
Installing the Required External/Separate Input Disconnect
An input disconnect must be installed in the line before the drive input terminals
in accordance with local, national, and international codes, such as NEC/CEC. If
an input disconnect is not installed as a factory option, the disconnect should be
sized according to the in-rush current as well as any additional loads the
disconnect might supply. The trip rating for the in-rush current (10 to 12 times
full load current) should be coordinated with that of the input isolation
transformer, if used.
Installing Input/Output Power Wiring
Table 16 - Style A Terminals
Table 17 - Style B Terminals
208V AC Hp 480V AC Hp Maximum Tightening Torque
Input Power
3…5 3…10 12 lb•in
7.5…10 15…25 35 lb•in
15…20 30…50 35 lb•in
25…50 60…350 275 lb•in
Output Power
3…10 3…20 26 lb•in
15…30 25…40 45 lb•in
50…60 49.5 lb•in
40…50 75…150 173 lb•in
200…250 260 lb•in
300…350 354 lb•in
208V AC Hp 480V AC Hp Maximum Tightening Torque
Input Power
3…5 3…10 12 lb•in
7.5…10 15…25 35 lb•in
15…20 30…50 35 lb•in
25…50 60…350 275 lb•in
Output Power
3…7.5 3…7.5 13 lb•in
10…20 10…30 19 lb•in
25…30 40…75 40 lb•in
100…150 275 lb•in
40…50 200…300 500 lb•in
350 375 lb•in