Installation and Upgrade Guide Owner's manual

Publication 1757-IN040B-EN-P - March 2002
ProcessLogix Client Installation and Upgrade Procedures 5-7
Removing Selected Components
The client upgrade process requires that you remove specific
ProcessLogix Software components.
Removing ProcessLogix Update
Removing Knowledge Builder
Removing PsAxCtl Document EXE
Removing Engineering Tools
Removing Quick Builder
Cleaning Up the Registry
Removing ProcessLogix Update
1. Click StartProgramsProcessLogix Engineering
Tools
Uninstall ProcessLogix Update.
2. At the Uninstall ProcessLogix Update window, enter 1.
Removing Knowledge Builder
Localization Localization settings are lost during the upgrade, reapply the settings
after the upgrade.
Station
configuration file
Winnt\station.ini
If you have made changes in the station.ini file, you will need to
reapply them to the new file after the upgrade. The
IconPopToTopOnAlarm option has been removed, and is no longer
recognized by Station.
Its replacement is FlashWindowOnAlarm, which enables Station to
flash its title bar and taskbar icon when an alarm is generated. This
behavior is disabled by default. DisConnectTimeout and
KeepAliveTimeout settings have been added, and are used to
configure fast Station failover. For details, see the
Configuration
Guide
.
Navigate in Knowledge Builder to
Server and Client Configuration
Guide
Configuring Stations and Printers
Using Station for
Configuration
for more information.
Station setup file The new default setup file is configured to as “static Station 1”. If this
is not correct, you must make the appropriate changes via Station’s
Setup menu. See the
Configuration Guide
for details.
Navigate in Knowledge Builder to
Server and Client Configuration
Guide
Configuring Stations and Printers
Setting Up Station
for
more information.
Table 5.A
Item Options