Manual

12 Rockwell Automation Publication 1512A-UM100F-EN-P - May 2013
Chapter 2 Installation – Standard Enclosure
3. Load cables for the power cell should be routed before control cables. Pull
the cables into the cabinet through the appropriate opening (see Figure 13
to Figure 15
).
4. Remove current transformer barriers.
5. Connect the cables to the current transformers and tighten the
connections to 65 N•m (48 lb•ft).
6. Connect cable shields (if present) to the ground lug.
7. Reinstall the current transformer barrier and reassemble the cabinet.
Figure 13 - Access to Load Cable Conduit Openings (Bottom Entry)
Figure 14 - Load Cable Conduit Openings, Bottom Exit