Keep the ACF60-00 in its packaging in which it was delivered throughout all the
moving stages. The packaging is only removed at the time of final installation.
Lifting the ACF
If the ACF must be lifted, connect cables to the openings on the supports at the base of
the ACF, and use support bars and spacers so that the cables don’t damage the ACF
panels while moving (see Figure 12).
The lifting crane and all the accessories (cables, tethers, bars) must be appropriate
for the job. See the “TECHNICAL SPECIFICATIONS” paragraph on page 11 for the
weight of the ACF. Robur S. p. A. cannot be held responsible for any damage that
may occur during the commissioning of the ACF.
Figure 12 – Example of bar and cables in the correct position for the lifting of the ACF60-00
ACF positioning and required clearances
The ACF must be installed outside the buildings and in an area with a good circulation of
air.
Installation inside a room of any type is not allowed.
The ACF can be installed at ground level, on a platform or on a roof, if the roof is able to
sustain the weight. The weight of the ACF can be found in the “TECHNICAL
SPECIFICATIONS” section on page 11.
The noise produced by the ACF during operation is mostly created by the condenser fan.
Even though the noise level is not high with respect to other electrical appliances of
similar power, the ACF should not be installed near rooms or surroundings that require
silence, such as bedrooms, meeting rooms and the like.