12 Beacon 110 Operator’s Manual
Chapter 3: Installation & Startup
Overview
This chapter describes procedures to mount the Beacon 110 Gas Monitor, make wiring
connections to the monitor, and start up the monitor.
WARNING: Perform all installation and start-up procedures in a “fresh air” environment
(environment known to be free of combustible gas, toxic gas, and of normal
oxygen content). The Beacon 110 is not in operation as a gas monitoring system
until the start-up procedure is complete.
Mounting the Beacon 110
Perform the following procedure to install the instrument housing at the mounting site.
Figure 6: Beacon 110 Outline & Mounting Dimensions
1. Select the mounting site. When you select the mounting site consider the following
factors: