5. PREPARATION BEFORE OPERATION
IMSRM52-E5
31
5.4 When the Power is Turned on for the First Time
Checking before power on
Check the following items, and then turn on the power of the control unit.
Operation environments conform to 3.1 Mounting Cautions (P. 15).
The wiring and connections conform to 4. WIRING (P. 23).
The power supply voltage conform to 2. SPECIFICATIONS (P. 10).
Checking after power on
Check that the RUN lamps on the H-PCP-G and H-LNK-A modules are flashing.
For details of the PLC, refer to the User's manual for Control & Communication Link
system master/local units of Mitsubishi Electric Co., Ltd.
5.5 Control Unit Operation When the PLC is Abnormal
When the Control & Communication Link is not normally connected after the
power to the control unit is turned on
As control start (RUN) cannot be set on the PLC side, control continues to stop (STOP).
The control unit starts with control RUN/STOP transfer set to the control STOP state
after power on. Set to control RUN on the PLC side after power on. However, if the
initialize setting (Extended communication) Control RUN/STOP holding (0: Not
holding prior to factory shipment) is changed to 1: Holding, control starts while the
state before STOP is being held.
For details of the Control RUN/STOP holding settings, refer to the separate
Supplementary Information for initialize settings [Extended Communication]
(IMSRM07-E).
When the PLC becomes abnormal while the control unit operates normally
The control unit continues its control at the temperature set value before the PLC becomes abnormal.