Installation manual
18 | RDV3611 Operation Guide: 11158-B 02-13
Commissioning
The installer must complete the installation and commissioning checklist below and
make sure this guide is left with you. They must also instruct you in the use and care of
the Symmetry, and make sure you understand the safety instructions and operation of
the appliance.
Checklist
F Appliance positioned in a suitable location (clearances etc.).
F Rinnai flue system installed and tested to ensure effective draw.
F Uprating kit installed if an LPG installation with a vertical termination.
F Gas pressure checked and set.
F Burn media installed as per instructions.
F Appliance tested for correct operation and to ensure no gas leaks.
F Customer instructed on operating procedure and safety requirements.
Installer details
Company name:
Installer name:
Address:
Phone: Mobile:
Certificate of compliance number for installation:
Signed: Date: