Installation Sheet

Installation & Servicing Instructions Rinnai E-Series
62
14.2.1 Visual inspection for general signs of corrosion
- Check all gas and water pipes for signs of corrosion.
- Replace any pipes that are corroded.
14.2.2 Measuring the ionization current
Seesubsection13.5“Measuringtheionizationcurrent".
14.2.3 Measuring the inlet gas pressure
Seesubsection6.4.1and.2“Gasconnectionwithnaturalgas"and"Gasconnection
with propane”.
14.2.4 Testing for gas leaks
Seesubsection13.1“Testingforgasleaks”.
14.2.5 Carrying out a pressure test of the heating system
Seechapter10.2“Fillingtheheatingsystem”.
14.2.6 Checking venting systems
Check the following points:
- Istheprescribedcombustionair/uesystemused?
- Havetheinstructionsforconguringtheuesystemasspeciedintherelevant
Installationinstructionfortheuegassystembeenobserved?
- Checkairintakeand/orairlteranduegasforobstruction,pollutionordamage.
When an air lter is used the air lter must be replaced yearly on boilers
operating in normal circumstances.
The conditions (eg. supply air quality) in which the boiler is installed should
be taken into account. This will show whether the frequency of replacement
should be reduced or increased. If in doubt, contact RINNAI.
NOTICE
i