Technical data
Commissioning
2.7 First commissioning, vector control mode in the chassis format
Commissioning Manual
96 Commissioning Manual, (IH1), 01/2011, 6SL3097-4AF00-0BP1
STARTER diagnosis options
Under "Component" -> Diagnosis -> Control/status words
● Control/status words
● Status parameters
● Missing enable signals
2.7 First commissioning, vector control mode in the chassis format
The example provided in this section explains all the configuration and parameter settings,
as well as the tests that are required for initial commissioning. Commissioning is carried out
using the STARTER commissioning tool.
Requirements for commissioning
1. The commissioning requirements have been met according to Section 1.1.
2. The check list - Table 1-1 or 1-2 from the Chapter Preparing for commissioning - has
been filled out and the points complied with.
3. The STARTER commissioning tool is installed and activated.
--> see the "Readme" file on the STARTER installation CD.
4. The power supply (24 V DC) is switched on.