Technical data

Commissioning
2.6 First commissioning control mode vector U/f in booksize format
Commissioning Manual
Commissioning Manual, (IH1), 01/2011, 6SL3097-4AF00-0BP1
89
2.6 First commissioning control mode vector U/f in booksize format
The example provided in this section explains all the configuration and parameter settings,
as well as the tests that are required for initial commissioning. Commissioning is carried out
using the STARTER commissioning tool.
Requirements for commissioning
1. The commissioning requirements have been met according to Section 1.1.
2. The check list - Table 1-1 or 1-2 from the Chapter Preparing for commissioning - has
been filled out and the points complied with.
3. The STARTER commissioning tool is installed and activated.
--> see the "Readme" file on the STARTER installation CD.
4. The power supply (24 V DC) is switched on.
2.6.1 Task
A drive, booksize format with vector U/f control mode with the following components is to be
commissioned for the first time:
Table 2- 10 Component overview
Designation Component Order number
Closed-loop control and infeed
Control Unit Control Unit 320-2DP 6SL3040-1MA00-0AA0
Smart Line Module Smart Line Module 10 kW 6SL3130-6AE21-0AAx
Line filter package 10 kW Line filter and line reactor 6SL3130-0GE21-0AAx
Drive 1
Motor Module Single Motor Module 5 A 6SL3120-1TE15-0AAx
Motor Induction motor 1LA
Drive 2
Motor Module Single Motor Module 5 A 6SL3120-1TE15-0AAx
Motor Induction motor 1LA
The enable signals for the infeed and the drive should be realized via terminals.