Technical data
Commissioning
2.5 First commissioning, servo control mode, booksize format
Commissioning Manual
82 Commissioning Manual, (IH1), 01/2011, 6SL3097-4AF00-0BP1
What to do? How to do it?
You have now created the project.
-> Click "Complete".
4. Summary
5. Configure the drive
unit.
Once you have created the project, you have to configure the drive unit. The following
sections provide some examples.
2.5 First commissioning, servo control mode, booksize format
The example provided in this section explains all the configuration and parameter settings,
as well as the tests that are required for initial commissioning. Commissioning is carried out
using the STARTER commissioning tool.
Requirements for commissioning
1. The commissioning requirements have been met according to Section 1.1.
2. The check list - Table 1-1 or 1-2 from the Chapter Preparing for commissioning - has
been filled out and the points complied with.
3. The STARTER commissioning tool is installed and activated.
--> see the "Readme" file on the STARTER installation CD.
4. The power supply (24 V DC) is switched on.