Technical data

Commissioning Manual
Commissioning Manual, (IH1), 01/2011, 6SL3097-4AF00-0BP1
13
Preparation for commissioning
1
Before commissioning observe the conditions described in this chapter.
The preconditions for commissioning must be fulfilled (in the next chapter).
The relevant checklist must have been worked through.
The bus components required for communication must be wired up.
DRIVE-CliQ wiring rules must be adhered to.
ON-OFF responses of the drive
1.1 Requirements for commissioning
The following are necessary for commissioning a SINAMICS S drive system:
STARTER commissioning tool
An interface, e.g. PROFIBUS, PROFINET, CAN bus or USS (RS232-C)
Completely wired-up drive line-up (see the Manual)
The following diagram shows a sample configuration with booksize and chassis components.