Contract Type and Values
The TAA waiver of the BAA applies to supply and construction contracts that
exceed a specified value.
Supply contract definition - Materials purchased directly by the government
Supply Contracts dollar threshold - $70,079.
Construction Materials definition - an article, material, or supply brought to the
construction site by the contractor or Subcontractor for incorporation into the
building or work. When a construction contract is estimated to exceed the
TAA thresholds, REC can supply construction material and components
thereof from any designated country.
Construction Contracts dollar thresholds - $7.8 million.
if the estimated value of the construction is more than $7,804,000 million, the
BAA is waived and the TAA procurement procedures apply.