Solar BAA ARRA Funding Information

12
© 2011 REC All rights reserved. Confidential
The applicable FARs
For U.S. government construction contracts, the responsibilities and obligations
of the Buy American Act and the Trade Agreements Act are imposed by four
contract clauses
For the Buy American Act,
the clauses are: FAR 52.225-9, Buy American Act Construction Materials (FEB 2009)
and
FAR 52.225-10, Notice of Buy American Act Requirement Construction (FEB 2009) if
the solicitation contains FAR
52.225-9.
For the Trade Agreements Act, the clauses are:
FAR 52.225-11, Buy American Act—Construction Materials under Trade Agreements
(AUG 2009) and
FAR 52.225-12, Notice of Buy American Act RequirementConstruction Materials
under Trade Agreements (FEB 2009) if the solicitation contains FAR
52.225-11.
Most contracting officers include all four clauses in their solicitations.