IMPORTANT: All flooring must be rolled with a minimum 100-lb roller after
installation. Use a hand roller in areas not reached with a 100-lb. roller.
Installation method for 12”x24” tile is running or stretcher bond see below
diagram (Figure 4)
After you have found the center of the room, take a tile and mark out the tile
width from the center point of the wall to make sure that you do not end up
with any cut piece smaller than 6” and adjust your mark at the center point
of the room if necessary. Use the same measurement for the center point of
the opposite wall. Proceed dry laying the tiles on half the room for optimal
cutting and minimal waste against walls and other obstructions. During dry-
lay procedure, make sure that tile joints do not coincide with the joints in the
subfloor. Spread adhesive on one side of the room when dry laying and cuts
are complete. Begin laying tiles from the middle of the room to the edge of
the room in the running or stretcher bond pattern shown below.
Figure 4
IMPORTANT: All flooring must be roller with a minimum 100-lb roller after
installation. Use a hand roller in areas not reached with a 100lb roller.