5. If this boiler is used in connection with refrigeration
systems, the boiler must be installed so that the
chilled medium is piped in parallel with the heating
boiler using appropriate valves to prevent the
chilled medium from entering the boiler, see Figure
5. Also, consult Residential Hydronic Heating
Installation and Design I=B=R Guide.
6. A hot water boiler installed above radiation level
must be provided with a low water cutoff device as
part of the installation. See Section X, Low Water
Cut-Off for additional details.
7. Oxygen Contamination:
a. There are many possible causes of oxygen
contamination such as:
i. Addition of excessive make-up water as a
result of system leaks.
ii. Absorption through open tanks and ttings.
Figure 4: Recommended Boiler Piping for Series Loop Hot Water System
iii. Oxygen permeable materials in the
distribution system.
b. In order to insure long product life, oxygen
sources should be eliminated. This can be
accomplished by taking the following measures:
i. Repairing system leaks to eliminate the need
for addition of make-up water.
ii. Eliminating open tanks from the system.
iii. Eliminating and/or repairing ttings which
allow oxygen absorption.
iv. Use of non-permeable materials in the
distribution system.
v. Isolating the boiler from the system water by
installing a heat exchanger.
See Section VI, Paragraph B for additional details.