User's Manual Part 1

Chapter 2 Installation and Setup WinLink 1000 Installation and Operation Manual
2. Connect the AC/DC converter 3-prong plug to a mains outlet.
The unit turns on automatically upon connection to the mains.
The green PWR indicator turns on, and the IDU indicator blinks
orange for approximately 40 seconds during startup. See
Normal Indicators
section in Chapter 3.
After approximately 20 seconds the ODU starts beeping. The
beeps continue until the ODUs are aligned and the link set up.
3. Wait for approximately one minute, then repeat for Site B.
Connecting Power to an IDU-C
AC power is supplied to the WinLink 1000 IDU-C through a standard
3-prong plug.
AC power should be supplied via a 1.5m (5 ft) standard power cable
terminated by a standard 3-prong socket. A cable is provided with the
unit.
Æ
To connect AC power to an IDU-C:
1. Connect the power cable socket to the power connector on the
WinLink 1000 front panel.
2. Connect the power cable plug to the mains outlet.
The unit turns on automatically upon connection to the mains.
Æ
To connect DC power to an IDU-C
A special IEC 60320 adapter for-48 VDC power connection is supplied
with the unit.
Connecting Power to an O-PoE
AC power is supplied to the O-PoE via a 3m (10 ft) 3-prong AC cable
attached to the unit (pigtail). The AC cable is provided with no
termination.
Æ
To connect AC power to an O-PoE:
Connect the power cable to a protected/shielded AC mains outlet. The
AC mains outlet should be provided with circuit breaker rated 5A
according to the local national electrical code.The unit will be turned
on automatically upon connection to the mains.
2-10 Connecting the Power