Installation Guide
Table Of Contents
- Title
- Contents
- Introduction
- System Description
- Pre-Installation
- Receipt of Equipment
- Site Planning
- Main Rack and Supporting Hardware
- Remote ACUs
- RFUs
- RadioBlades
- RAPs
- URU
- Interconnecting Cabling
- Main Rack Configuration
- RF Planning
- Site Survey
- Alarm Configuration
- Tools Required
- Installation
- Equipment Commissioning
- iDEN Interface
- Power Plant
- RadioFrame System
- Coverage Validation
- Site Acceptance Guidelines
- RadioFrame System Functionality Test
- RadioFrame System iDEN Functionality Test
- Interconnect & Dispatch Setup & Voice Quality
- Packet Data Service Connection and Latency
- Short Message Service
- Handover and Cell Reselection
- Interconnect Connection Stability and SQE Performance
- Dispatch Connection Stability
- Idle SQE Testing and Validation
- System Self-Recovery Test
- Packet Data Stability and Throughput
- Validation of ‘Unable to Key BR’ Alarm
- Rectifier & AC Power Alarms
- iSC-3 Functionality Test
- RadioFrame System iDEN Functionality Test
- Connecting the RFS to the Customer LAN
- Operations and Maintenance
- Appendixes
RadioFrame System
Appendix B: Site Survey
RFN_3.1 Beta 141
Site Survey REV A
Carrier Date
Customer
Project #
Site Location
RFN Project Engineer
Present for Site Survey Name Email Phone
Carrier representative
Customer representative
Building/Site Manager
Installation vendor
RFN Engineer
RFN Project Manager
Other
Customer Expectations
Who will provide RF measurements?
Who will install the RFS?
Who will commission the installation?
Will the RFS be shipped directly to the site or staged?
Will the RFS be assembled and tested at the customer site?
Digital photos permitted during the site survey?