User's Manual
RadioFrame System Method of Procedure GSM/802.11b
Final Checkout
68 RadioFrame Networks, Inc.
- T1/E1 repeater shelf / cfl cabinet location
- T1/E1 level at extended demarc (RJ48 x jack)
• Summary
- log book at site with recent entry
- outstanding issues/punch list items for site
- defective equipment found/replaced
5.5.2 Site As-Built Acceptance Test Procedures
Complete the test procedures described in this section to record the site as built.
5.5.2.1 Grounding
Record the following grounding information. For any unacceptable item, take corrective
action and record what occurred, or record the item for the next site visit.
Yes No
Buss Bar O.K. (optional)
BCU/ACU rack(s)
5.5.2.2 T1/E1 Line
Record the following information for the T1/E1line.
T1/E1 circuit ID # Primary Secondary
T1/E1 surge arrestor installed/grounded
Yes
No
T1/E1 repeater shelf/cfl cabinet location
Inside
Outside
T1/E1 level at extended demarc (RJ48x jack)
+/- dbsx
Voltage
5.5.3 RadioFrame System As-Built Documentation
As-built documentation for the RadioFrame Networks equipment includes the following:
• Equipment inventory
• Cabling pathways
• Floor Plan with site configuration and component locations
5.5.3.1 Equipment Inventory
The final Equipment Inventory should show the following information for the RFS
components installed:
• Part number
• Serial number