4.4 Installation Gigabit Ethernet Switch (GES)
GES is designed to be mounted into a 19” rack. Remove the GES from its packaging and
check for obvious signs of physical damage. If the unit is physically damaged do not proceed
with the installation. Check the packing for completeness according to the packing list.
To mount the GES to a rack, the angles that are delivered with the accessory kit have to be
fixed to the housing. Voltage of mains must 115/230 VAC ± 10%. Connect the mains cord
(from the accessory kit) to the rear connector of the GES and install the GES at its
designated place within the rack.
Interconnection of the GESs
Use IP ports 11 and 12 to connect the GES with other GESs. Port 11 and 12 are identical to
SFP ports 1 and 2. Use either IP port 11 OR SFP port 1. Use either IP port 12 OR SFP port
2.
After the physical setup has been performed and the BSIs and RRHs have been connected
to the GES, the IP setup can be done. This is described in section 4.7.3.
4.5 Installation Base Station Interface (BSI)
BSI is designed to be mounted into a 19” rack. Remove the BSI from its packaging and
check for obvious signs of physical damage. If the unit is physically damaged do not proceed
with the installation. Check the packing to completeness according to the packing list.
The BSI is ready to be installed directly at its designated place into the rack using the
accessories from the accessory kit. The BSI is power supplied via Ethernet (PoE), but there
is also an external power supply available, input voltage 90 – 264 VAC, output voltage
48VDC.
4.6 Installation NMS Server (Hardware)
Remove Network Management System Server for ClearFill®Star (CFS-NMS-1) from its
packaging and check for obvious signs of physical damage. If the unit is physically damaged
do not proceed with the installation. Check the packing to completeness according to the
packing list.
Install the NMS Server into a 19” rack. Connect a monitor, a keyboard, and a mouse (to be
provided locally) to the server using the appropriate interfaces on the front side.
Voltage of mains must be 115/230 VAC ± 10%. Connect the server at the rear side to mains
(cable to be provided locally).
Connect the server via its LAN connector (RJ45 on the front side) to the GBit Ethernet Switch
(CFS-GES-1) with a LAN cable (to be provided locally).
The CFS-NMS-1 installation is completed now.