Specifications
LA-210 Ver. 1.5 Site Requirements and Prerequisites 2-1
Chapter 2
Installation and Setup
LA-210 is delivered completely assembled, and is factory set for basic operation.
It is designed for installation as a desktop unit or for mounting in a 19-inch rack.
For rack installation instructions, refer to the
Rack Mounting Kit for 19-inch Racks
guide that comes with the RM kit.
After installing the unit, use an ASCII terminal connected to the CONTROL port to
perform any configuration necessary. The configuration procedures are described
in
Chapter 3
and
Chapter 4
.
If problems are encountered, refer to
Chapter 6
.
No internal settings, adjustment, maintenance and repairs should be performed
by either the operator or the user. Such activities must be performed only by
skilled personnel who are aware of the hazards involved.
Always observe standard safety precautions during installation, operation, and
maintenance of this product.
Before installing the product, review Handling Energized Products
at the
beginning of the manual.
2.1 Site Requirements and Prerequisites
AC-powered LA-210 units should be installed within 1.5m (5 feet) of an easily
accessible grounded AC outlet capable of furnishing the required supply voltage,
in the range of 100 to 240 VAC, 50 or 60 Hz.
DC-powered LA-210 units require a -48 VDC power source, which must be
adequately isolated from the main supply.
Allow at least 90 cm (36 in) of frontal clearance for operator access. For
continuous product operation allow at least 10 cm of frontal clearance and at
least 15 cm at rear of the unit, for cable connections and ventilation. For proper
ventilation, keep at least 2.5 cm clearance from the sides and top of the product.
The ambient operating temperature of is 0º–50ºC (32º–122ºF), at a relative
humidity of up to 90%, non-condensing.
Warning
Note