Installation Guide
Complete the Installation
1. Install the finished flooring according to the manufacturer’s instructions.
2. Retest the mats to ensure that the mats have not been damaged during the installation process. If they have
been damaged, follow guidelines noted to remedy the situation.
3. Install Underlayment.
For all floors, install a suitable underlayment such as QuietWalk, QuietWalk Plus, or QuietWalk LV underlayment
over the subfloor and over any vapor barriers that were needed for installation over concrete or at below grade.
Place Caution Stickers
Apply warning stickers provided with mats in appropriate locations, as shown below. these labels are an integral
part of this heating system and must be installed for warranty to be in force.
4. Inspection and Testing Continued
Installation & Owner’s Guide 16
Install baseboards or trim around the perimeter of the room. This ensures that the
oor will not lift, exposing the mats. The ooring manufacturer’s instructions will have
information about installing the baseboard or trim to allow the oor to oat properly.
NOTE: