80-J7615-1 Rev. A MAY CONTAIN U.S. AND INTERNATIONAL EXPORT CONTROLLED INFORMATION 7-5
Installing the TT210 Terminal on Containers Installation
3. Carefully ascend the scaffolding to where the terminal will be installed and place it as
high up as is practical between the vertical support rails in the 7-way bay. Make sure it’s
at least .50 inch from the top.
4. Mount the unit on the driver side of center using the six rivets. These should be installed
top, top, middle, middle, bottom, bottom.
a. Drill a 3/16” hole then attach the first rivet.
b. Level by either using a template or by measuring down from the top rail on both
sides.
c. Drill another hole and attach the second rivet, then do the same for the rest of
rivets.
5. Determine if installing a cargo sensor.
6. If using a cargo sensor, determine the cargo sensor wiring. It can be wired externally or
internally. Internal installation requires a 7/8” hole for the cargo sensor cable.