E. Finishing Material
It is important that the nishing material is determined before
the appliance is secured to the oor. Depending on the n-
ishing material and installation method, the appliance may
need to be positioned further in or out of the wall.
There are three ways nishing material can be applied:.
1. Behind the mounting frame
. Flush with the mounting frame
. Proud of the mounting frame
1. Behind the Mounting Frame
The mounting frame is designed to have a 1/ inch (1mm)
overlap on the sides and the top of the framing opening.
Figure 28.1.
NOTICE: Non-combustible material is not needed to nish
this appliance.
Positioning the nailing anges:
• Slide the nailing anges all the way to the front and this
will set the appliance for 1/ inch (1mm) sheet rock.
• If tile, marble or other at surface nish material is desi-
ered and you want the mounting frame to cover the cut
edge, set the nailing anges at a dimension of the sheet
rock thickness plus the nishing material thickness.
Figure 28.2.
Example: Sheetrock = 1/2 inch (13mm)
Finish Material = 3/8 inch (9.5mm)
Move ange: 7/8 inch (22mm)
2. Flush with the Mounting Frame
The nish material can not be thicker than 1-1/ inches
(8mm) to use this method. Figure 28.3.
• Set the nailing anges for sheet rock thickness and
install the appliance.
• Install the mounting frame.
• Install the nishing material to edge of the mounting
frame.
3. Proud of the Mounting Frame
This method is mainly used for a brick or stone installation.
When nishing material is proud of the mounting frame
and front, there must be a 1-1/4 inch (mm) airow clear-
ance in front of the mounting frame. Figure 28.4.
Use the masonry spacer supplied with the Front to position
the nishing material at the proper dimension. Remember
to keep the Front opening clearances in mind when nishing
material is proud of the Front. (See pages 29-30) .
Set the nailing anges for sheet rock thickness and
install the appliance.
• Install the mounting frame.
• Install the nishing material to edge of the mounting
frame.
Complete the installation following all specied clear-
ances to combustibles.
Figure 28.1.
Figure 28.2
Figure 28.3.
Figure 28.4.
Adjustable Nailing Flange
Adjustment Screw
Front of Fireplace
7/8 in
(22mm)
Mounting Frame
Finishing Material Behind
the Mounting Frame
Mounting Frame
Finishing Material Flush
with Mounting Frame
Door Frame
Finishing Material Proud of the Door Frame
Maintain 1-1/4 inch (32mm) air
clearance in front of door frame
Masonry Spacer