Installation guide
1–Installation
12800-360 Installation
D000140-001 D 1-35
Installation Tasks
1. Install clip nuts: If applicable, remove the doors of the rack. Install M6 clip
nuts in the following locations on EIA rails for U5 installation. For U6
installation, increment clip nut locations by one U (1.75”).
Figure 1-29. Clip Nut Installation
For improved stability, orient the clip nuts as shown (i.e., orient the flanges
horizontally):
NOTE:
It is recommended that 12800-360 is installed into the rack at 5U or 6U
location. This will locate the chassis approximately 12" from the floor and will
allow the chassis to be moved onto the support rails by sliding off the pallet.