Installation manual
PCX 256 PROGRAMMING MANUAL
RINS868-6 Page: 53
Test Bell?
To Test the Bell press the key. All outputs
programmed as either Bell or Strobe will be
tested. “Testing Bell will be displayed” Press the
key to stop the test. ‘Test Bell’ will be
displayed, press the key.
Do Battery Load Test?
To perform a Battery Load Test, press the
key.
The Battery Load test will be started.
Once the Battery test has completed, press the
key, ‘Do Battery Load Test’ will be displayed,
press the key.
Test PGMs?
To test the PGMs press the key.
Select the PGMs you would like to test (see page
38 for the PGM types) and press the key.
All outputs programmed as the type selected will
be active. Press the key. The outputs will
switch off. Repeat for other output types as
required. Press the key. ‘Test PGM’s’ will be
displayed. Press the key.
Test PHC Communications?
To test the PHC Communications press the
key. This test is necessary to gain
authorisation for connection to the network for
SMS communication.
‘Press Y if using PABX or N if not’ will be
displayed. Press the key if you are using a
PABX system or the key if not.
Press the key once it has completed. ‘Test
PHC Communications’ will be displayed, press
the key. You will be returned to the Engineer
Menu.
If the test has failed please see page 65.