User Manual

45
Annex 1: Installation and System Turn ON Progress List
Tick after
completion
No.
Item
Remark
1
The environment is meeting all technical
requirements.
3.3.1 Cleaning
3.3.2 Temperature
3.3.3 Fire-extinguisher System
3.3.4 Grounding System
3.3.5 Clearance
Refer to chapter 3.3
2
Selection of installation sites.
Refer to chapter
3.4.3.
3
Battery base is installed follow the technical
requirements.
Refer to chapter
3.4.4.
4
Battery modules installation.
Refer to chapter
3.4.5.
5
Battery system are fixed.
Refer to chapter
3.4.6.
6
Control Module (BMS) and Battery Module are
installed well.
Refer to chapter
3.4.7.
7
Connect D+ and D- between BMS to the
inverter/PCS or confluence cabinet.
Refer to chapter
3.5.2.
8
Connect the grounding cable.
Refer to chapter
3.5.1.
9
Double check every power cables, communication
cables, grounding cable installed well.
Refer to chapter
3.5.2 and 3.5.1.
10
Switch the external power or inverter/PCS on,
ensure all the power equipment can work
normally.
Refer to chapter
3.6.4.
11
The first installation should do full charging progress
automatically.
If the status LED of BMS turns to blue, it means this
battery string is operation.