1.   The use of a bypass assembly is recommended in case the system requires ‘off-line’ maintenance. If this is the case, 
it must be noted that the system will require supplementary disinfection of the distribution system if any water is used 
during this bypass condition. In addition, during bypass, the water will NOT be disinfected until such time as the system 
is sanitized and returned to service. Please refer to the complete disinfection procedure as outlined on page 7 of this 
document. If the water is to be offline, the water must be boiled for twenty minutes prior to consumption.
2.   Select a suitable location for the disinfection system and its related components. As it is recommended to install a 
ground fault protected circuit (GFCI), make sure that this is taken into consideration prior to any installation. The system 
can either be installed vertically (inlet port at the bottom) (Figure 1A), or horizontally (Figure 1B), When selecting a mount-
ing location, you must also leave enough space to allow for the removal of the UV lamp and/or quartz sleeve (typically 
leave a space equal to the size of the reactor chamber itself).
  Pre-Installation Instructions
   The figure below shows the proper water flow for horizontal or vertical installation. Make certain that your unit and the 
inlet and outlet pipes are in the right position for either horizontal or vertical installation
NOTE: when installing in horizontal direction, please make sure that UV chamber is on a slope to allow water to be 
drained during servicing