Technical data

-
22
7) a step of operation.
3) 4 bolts black coats which the inside lining squeeze out, take
down the inside lining black cover(Figure 21)
4) Based on the coding switches shown as Figure 2, set up the
protocol used by the camera and the baud rate as per the
state according to Table 2. Check the address of the camera
to see if it is matched with that you need. If not, set the
address of the dome camera at corresponding position as per
Table 1
Figure 20 Figure 21
5) Installs the inside lining black cover(Figure 22)
6) Installs the transparent vitreous cover (Figure 23)
Figure 22 Figure 23
7) Take out the cover of the wall-installed bracket(Figure 24)
8) Take out system control wires from the bracket(Figure 25)