Outlets
Delay Mode
Pressing the right arrow pulls up the next menu of the Setup section.
The P15 has a lot of outlets. 10 total in the US version, (other regions will have dierent amounts as
outlet sizes vary). The outlets are grouped into Zones that can be personalized to t your specic
system requirements.
The Power Plant 15 allows for six dierent power sequencing options. The default
setting for all zones is SWITCHED. All of these selections are only activated by the front-panel
power button.
1. SWITCHED: As the front-panel power button is engaged, any zone set to SWITCHED will
power up with no delay, and power down with a three-second delay.
2. DELAYED: As the front-panel power button is engaged, any zone set to DELAYED will
power up with a three-second delay, and power down with a zero-second delay.
3. PROGRAMMED: As the front-panel power button is engaged, any zone set to
PROGRAMMED will power up with a delay in the number of seconds desired, as well as
power down with a delay in the number of seconds desired.
4. REBOOT: As the front-panel power button is powered down, any zone set to REBOOT
will power down accordingly, and will after a three-second delay power back on. This mode is