Volta 42” & Volta 32” Pryzm Inset Fire Conversion Kit Instructions for installation Patent pending UK Registered Design R4 June 2021 200799_1 1
Contents Conversion Kit Check List Installation- Introduction Assembly- Pre-fabricated Chimney Breast Assembly- Existing Masonry Chimney Breast Assembly- Fire Conversion Kit Installation Assembly- Fire Conversion Kit Installation continued Installation- Positioning the fire Installation- Magnet Bracket Installation- Fixing the Fire Installation- Fixing the Fire continued Installation- Fitting the Trim Maintenance 200799_1 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 P13 P14 2
Conversion Kit Check List 18 X No.8 x15mm Domed-Head Screws 4X No.8 x13mm Pan-Head Washer Screws 1X 1000L Trim or 750L Trim Dependant on the model purchased 4X 10 Ø x 4mm Magnets 4X Angle Brackets 1X Pre-assembled 1000L or 750L MDF Framework Dependant on the model purchased Note: Please be sure to take extra care when removing the trim from the packaging and handling it during installation.
Installation Introduction Before the product can be installed, consideration will need to be given to routing the power supply to the fire. This will affect the stages of the installation process. We advise a qualified electrician conduct any electrical parts of the installation. Note: A single wall socket is required for the operation of the fire, please refer to the separate fire instructions for further information.
Assembly- Pre-fabricated Chimney Breast Before commencing further with the installation please ensure the 2 X Fire Support Brackets have been attached to the MDF Framework, these set the minimum depth required for installation- 238mm. As shown on Page 4. Decide on the installation height of the fire and construct the studwork around the MDF Framework. The studwork construction in Diagram 2 is for guidance only.
Assembly- Existing Masonry Chimney Breast Before commencing further with the installation please ensure the 2 X Fire Support Brackets have been attached to the MDF Framework, these set the minimum depth required for installation- 238mm. As shown on Page 4. We recommend sealing the MDF Framework using an appropriate sealer, especially if the installation site is damp, however this is down to the discretion of the installer.
Assembly- Fire Conversion Kit Installation Diagram 6 Remove the existing fire side panels from either side of the fire, as shown in Diagram 6. Retain the 10 x No.8 x12mm Domed-Head Screws. 5 x per side. The side panels are no longer required and can be discarded. Diagram 7 If applicable remove the transit brackets from the bottom of the fire, as shown in Diagram 7. Remove the 4 x No.8 x12mm Domed-Head Screws. The transit brackets and screws are no longer required and can be discarded.
Assembly- Fire Conversion Kit Installation Continued …… Fix the 4 x Angle Brackets using the previously retained- No.8 x12mm Domed-Head Screws. 2 x per bracket. Ensure the brackets are fixed in the correct orientation- the small tab on each bracket should be positioned, as shown in Diagrams 8 & 9. Tab Diagram 8 The tabs are used to ensure the brackets are installed at the correct distance from the finished wall surface in later procedures.
Installation- Positioning of the Fire Note: Dependant on the model purchased the fire may require a two adult person lift. Diagram 10 Diagram 11 Note: Before positioning the fire, connect the fire to a power supply. The next step is to position the fire in the opening. Angle the fire into the opening, as shown in Diagram 10, taking care not to damage the bottom long edge of the finished opening.
Installation- Magnet Bracket With the fire pushed to the rear of the opening. Install the Magnet Bracket, as shown in Diagram 12, using the supplied 2 x No.8 x15mm Domed-Head Screws, to fix into the pre-drilled holes in the MDF Framework, this will ensure the bracket is fitted centrally in the opening. Before fixing in position align the tabs on either end of the bracket with the face of the finished wall surface, as shown in Diagram 13.
Installation- Fixing the Fire Pull the fire forward to the front of the opening and centralise. Align the tabs on the angle brackets with the face of the finished wall surface, as shown in Diagram 14. Fix through the slot in each bracket, into the pre-drilled holes in the MDF Framework using 4 x No.8 x15mm Domed-Head Screws, whilst aligning the tabs with the face of the finished wall surface, as shown in Diagram 15.
Installation- Fixing the Fire continued….. Diagram 17 Diagram 18 Remove the protective film. Position the side panels down the sides of the opening between the fire body and the brackets, as shown in Diagram 17. Secure in position using the 4x No.8 x13mm Pan-Head Washer Screws, as shown in Diagram 18. Magnet Diagram 20 Magnet Diagram 19 Attach the 4 x Ø 10 x 4mm Magnets in postion. 1 x in each bottom corner of the opening, onto the metal side panels, as shown in Diagram 19.
Installation- Fitting the Trim Diagram 20 Note: Please handle the trim with care when positioning. Finally offer the trim into the opening, engaging the magnets along the bottom edge, as shown in Diagram 20. Diagram 21 Once in position secure though the slots on the underside of the trim into the pre-drilled holes in the MDF Framework, using 4 x No.8 x15mm Domed-Head Screws, as shown in Diagram 21.
Maintenance WARNING: Before any maintenance or whilst cleaning the exterior of the fireplace, the unit should be disconnected from the power supply until it has cooled down. Cleaning the Fire & Trim Cleaning or polishing products are not recommended. Fingerprints or other marks on the front glass panel can be removed by a piece of soft, damp, lint-free cloth with a good quality household glass cleaner. The front glass panel should always be completely dried with a clean, lint-free cloth or paper towel.