Specifications
362 Module 137: System Commissioning | System Commissioning Tools
System Commissioning Tools
Protege GX has a number of built in features that can be used when commissioning a system.
Item History
All programmable items in Protege GX have a History tab.
This tab shows the audit trail for the currently selected item, including who made a change to the programming
and when. This can be very useful in tracking down why something that was working has stopped working.
The History tab also shows details of what was changed. Highlight the change and click Details.
Both the old and new values are logged.
Where multiple changes were made in a single operation, these will be logged as one change.
The history tab currently only logs the changed values where the field contains a single value. Where there are
multiple values, such as doors in a door group, the values are not logged only the fact that something was