Piping Installation
1) Removepartsbagfromboilercrate.
2) Installsafetyvalve(spindlemustbeinverticalposition)intotappingonboilerleftside(seeFigure1)usingthe3/4”NPT
nippleandelbowsupplied.
3) Pipethedischargeofthesafetyreliefvalvetoalocationwherewaterorsteamwillnotcreateahazardorcauseproperty
damageifthevalveopens.Theendofthedischargepipemustterminateinanunthreadedpipe.Ifthesafetyvalve
dischargeisnotpipedtoadrainitmustterminateatleast6inchesabovetheoor.Theterminationofthesafetyvalve
dischargepipingmustbeinanareawhereitisnotlikelytobecomepluggedbydebrisorsubjectedtofreezing.
4) Installdrainvalveintotappingonboilerleftsideusingthe2x3/4bushingprovided(seeFigure1).
5) Connectsystemsupplyandreturntoboiler.SeeFigure7.FORCESTM03throughFORCESTM06maybepipedwith
oneortworisers.Install2”pluginTappingGifoptionalsecondsupplyAisnotused.Twosupplyrisersarerequiredon
theFORCESTM07andFORCESTM08.
6) PipingwithaChiller-Iftheboilerisusedinconjunctionwithachiller,pipetheboilerinparallelwithchiller.Use
isolationvalvestopreventchilledwaterfromenteringtheboiler.
DANGER
PIPESAFETYVALVEDISCHARGETOASAFELOCATION.
DONOTINSTALLAVALVEINTHESAFETYVALVEDISCHARGELINE.
DONOTMOVESAFETYVALVEFROMFACTORYLOCATION.
DONOTPLUGSAFETYVALVEDISCHARGE.
DONOTINSTALLASAFETYVALVEWITHASETTINGGREATERTHAN15PSI.