Installation manual

67
EN
Operating the PV inverter
NOTE
If selecting Germany or Italy as the country, it could be necessary to
adjust active and reactive power settings (Information for the settings
will come from the local grid operator).
If needed please call the local support hotline for assistance in setting
up Germany MVD/LVD or Italy CEI 0-21/A70 grid settings.
4. Start up the inverter:
After nishing the basic settings, turn on DC switches (including the DC switch in in-
verter), inverter will do some self-tests and start a countdown if there is no problem.
When operating, check all information on the display is correct (ex. Input voltage, current
and power; output voltage, current, power and frequency)
When solar irradiation is sufcient, the device will operate automatically, after the self-auto test is
completed successfully (about 2 minutes on the rst startup of a day). Please refer to Figure 7.2
showing the LCD Display and Control Panel details. The display includes a 5“ graphic LCD with
320x240 dots of resolution and a LED indicator showing inverter status. There are green and red
colored LED indicator lights to represent various inverter states of operation. Please refer to Table
7-1 for more detail on the LED indicator.
ESC: ESC MENU
DOWN: MOVE DOWN
UP: MOVE UP
ENTER: ENTER MENU OR CONFIRM
LED Indicator (GRN/RED)
LCD Display
Figure 7.2.: LCD Display and Control Panel