Power Up Sequence
Use the following procedure to power up unit:
Step 1. At house service main breaker, turn power ON.
Step 2. At rear of Disconnect, verify all phase indicators are lit (Figure 6).
Figure 6: Phase Indicators Location
Step 3. At front of Disconnect, check AC voltmeters. Voltages should read as follows:
Step 4. If meter readings are nominal, switch Main Breaker to the ON position (Figure 4).
Step 5. Verify that test point readings match LED meter readings for proper voltage.
Note
: Since the test points are
after
the Main Breaker, their voltages may be slightly lower than those indicated by the digital meters when
the Disconnect is under load. This is due to the internal resistance of the breaker causing a slight voltage
drop when current flows through it.
Note: The Pilot Light indicates when Main Breaker is energized (Figure 4). Press to test LED before Main Breaker is
"ON."
Voltmeter Connection Voltage
Neutral to X 120V ± 5V
Neutral to Y 120V ± 5V
Neutral to Z 120V ± 5V
X to Y 208V ± 8V
Y to Z 208V ± 8V
Z to X 208V ± 8V
YØ
ORDER:
MUST BE MADE
IN THE FOLLOWING
INPUT CONNECTIONS
1) CONNECT GROUND
2) CONNECT NEUTRAL
3) CONNECT PHASES
DISCONNECT IN
REVERSE ORDER
120/208V 3Ø INPUTS 400A PER Ø MAX
NEUT
GND
XØ
NEUT
XØ YØ
NEUT XØ
ZØ
ZØ
ZØ
DISCONNECT
Phase Indicators