2 INSTALLATION
2.1 INITIAL SETUP AND TEST
Before connecting the unit to the powerline, the user should verify the line cord is of the
proper gauge (Refer to para. 1.2.2 for loading requirements) and the safety ground is
connected. The user should verify the unit is configured for the proper input voltage. To
determine the proper configuration check the top of the unit for appropriate marking.
2.2 RECONFIGURING THE INPUT LINE VOLTAGE
To reconfigure the input line voltage the following steps must be performed.
1. Verify the input power is removed.
2. Remove the top cover and locate T1.
3. Use Table I for proper placement of wires.
4. Refer to figure below for terminal location.
Table 1 – Wire Placement
For 115 VAC OPERATION
T2-49Black #203
CB116Black #143
FAN9Black #202
T2-39W/Black #202
T2-29W/Brown #202
T1-216White #142
T1-316Black #142
T2-19Brown #201
FAN9White #201
CB116White #141
FOR 220 VAC OPERATION
T2-39W/Black #203
T2-49Black #203
T1-316Black #143
FAN9Black #203
CB116Black #143
T2-19Brown #201
T2-29W/Brown #201
T1-216White #141
FAN9White #201
CB116White #141
FOR 115 VAC OPERATION
FROM LOCATIONMETRIC SIZEWIRE COLOR AND GAUGELUG #