Product Manual
Operation
39
Connect Parallel
Cables
1. Secure the parallel kit to the 3kw generator handles as shown below.
2. Connect the red parallel operation cable to the parallel operation
outlets designated with the red O-ring on each of the generators.
3. Connect the black parallel operation cable to the remaining parallel
operation outlets on each of the generators.
4. Connect the green/yellow parallel operation cable to the grounding
post on each of the generators.
Starting the
Generators
1. Start one generator and make sure that the output indicator light on
the control panel is green.
2. Start the second generator and make sure that the output indicator
light on the control panel of the second generator is green.
Connecting
Appliances
1. Plug an appliance into the 50A receptacles on parallel kit.
2. Turn on the appliance.
Note: If either generator is overloaded, or if there is a short circuit in a
connected appliance, the overload indicator (red light) on the control panel
will go ON. The overload indicator (red light) will stay ON, and after about
4 seconds, current to the connected appliance(s) will shut off, and the output
indicator (green light) will go OFF. Stop both generators and investigate the
problem. Determine if the cause is a short circuit in a connected appliance
or an overload. Correct problem and restart the generators. Substantial
overloading may damage or shorten the service life of the generator.
Note: For single generator operation, the parallel operation cable must be
removed.
WARNING:
Never connect or remove the parallel operation cables when one or both generators
are running.
Item # 42411 (2 KW)
+
Item # 792220 (3 KW)
Item # 792220 (3 KW)
+
Item # 792220 (3 KW)