Owners manual
©2015 POISON SPYDER CUSTOMS 951-849-5911•WWW.POISONSPYDER.COM
INSTALLATION INSTRUCTIONS INST-14-51-030_A
TJ BFH™
Body
Mounts
IMPORTANT: Thank you for purchasing this Poison Spyder product. Please read through this entire document before proceeding with installation. If you are not
confident in your mechanical skills, please seek the help of a professional to perform the installation. Check your packages immediately upon arrival to ensure that
everything listed is included, and to check for damage during shipping. If anything is missing or damaged, or if you need technical assistance with any aspect of
this installation, call Poison Spyder at (951) 849-5911 as soon as possible. This document last updated May 2015.
APPLICATIONS
These installation instructions apply to the following
Poison Spyder products:
14-51-030 TJ BFH™ Body Mounts
PARTS LIST
(4) Long BFH™ Body Mount
(2) Short BFH™ Body Mount
TOOLS NEEDED
• Floor Jack or screw-type jack stand
• 3/4” socket, ratchet and torque wrench
• Cutting torch, plasma cutter, electric or pneumatic cut-off
tool or reciprocating saw
• Grinder with grinder wheel and flap wheel
• Welder
• Primer and paint
BEFORE YOU BEGIN
If your Jeep’s rubber body mount bushings are worn,
it would be advantageous to replace them as part of
this installation, as the bushings themselves are used
to assist with proper placement of the body mount
perches prior to welding. If you are installing a body
lift at the same time, you are advised to perform the
complete body lift installation, on to the stock body
mount perches, prior to continuing with the following
procedures.
INSTALLATION PROCEDURE
1. Park the Jeep on a flat, level surface and set the
parking brake.
2. From under the Jeep, observe the three factory body
mounts along the frame rail on each side, to determine
which two are “long” and which one is “short”, and lay
out each of the BFH Body Mounts accordingly
3. Use the 3/4” socket and ratchet to loosen each
body mount bolt. Depending on the age of the Jeep and
weather and road conditions in your area, they may
take some “persuasion” to loosen. Because of this, we
recommend ensuring that all 6 are loosened, and then re-
tightened before proceeding with the replacement of each
body mount individually.
The following steps pertain to the individual
replacement of a single body mount. The process will
be repeated for all 6 body mounts.
4. Position the floor jack or screw-type jack stand
underneath the Jeep’s body, close enough to the specific
body mount you will be working on to act as a temporary
support, but not so close that it hinders your access to work
around the body mount. Pump the jack up until it just
touches the Jeep’s body, but doesn’t try to lift it.