Installation Guide
4
REV-11 19, 12
Faucet Installation
5. The hot and cold side valves(H) are marked with ‘HOT’ and ‘COLD’ on
the valve. Place washer(I) underneath of the ‘HOT’ side valve. Slide
the valve through mounting hole. Place rubber washer(J) and steel
washer(K) to the valve from underneath of the mounting surface.
6. Ensure the handles are position correctly. Tighten the locknut(L) to the
valve(H) with the help of 1-11/32” socket. Install the ‘COLD’ side valve
same as ‘HOT’ side valve.
7. Connect the valve outlet hose connector(M) to the cross connector(F).
8. Connect HOT and COLD inlet to inlet supply lines carefully. Ensure all
the connections are installed correctly.