Installation Instructions

XL1000Pro
Retrofit Instructions
16. Disassembly of the XL1000 is complete with the exception of the crossbars running from the front
of the rack to the back of the rack. Remove all cross bars, swing doors, and support panels on the sides of
the rack. At this time the rack should be free of all obstructions on all sides of the rack.
ASSEMBLING THE XL1000Pro
1. Unpack all boxes and make sure you have received everything on the parts list. If you are missing
any part of the XL1000Pro retrofit kit then please call Pineapple Technology, Inc. at 916-663-1016
2. Starting at the back of the transmitter open the junction box. Locate the knock out in the side
facing the front of the transmitter. Punch out the 1 inch knock out. NOTE: In some junction boxes there
are no knockouts, as an alternative drill a 1 inch hole to accommodate the main power supply cable. Feed
the PS130-28 power cable through the hole made by the knock out.
3. From the front of the transmitter place the circuit breaker cables #1 & #2 through the rack and
secure the breaker panel to front of transmitter.
4. From the back of the transmitter run the breaker cables along the side of the rack and secure them
with a tie wraps as required. Then run the breaker cables along the bottom left side of the rack. Secure
breaker cable to the back left side of the transmitter ensuring the cable has a straight path to the junction
box.
5. Insert breaker cables into the junction box, using the hole closest to the front of the transmitter, on
the side of the junction box. Place the main power cable through the bottom of the rack and feed it through
the hole located on the side of the junction box towards the back.
6. With a wire nut connect the red wire from the main power cable to the red wire coming from
breaker wire #1. In turn connect the black wire from the main power cable to the black wire coming from
the breaker cable #1.
7. From the Main Power Cable secure the Ground (green) wire to the left side of the terminal strip in
socket #1. Then secure the Neutral (white) wire to the left side of the terminal block in socket #2.
8. From the Breaker Power Cable #2 secure the red wire to the left side of the terminal strip in socket
#3. Then secure the black wire to the left side of the terminal block in socket #4.
9. Connect the Ground (green) wire from the PS130-28 Power Cable atop the other wire into the
left side of the terminal strip in socket #1. Insert the 2 Ground (green) wires from the 110VAC plugs into
the right side of the terminal strip socket #1.
10. Place both the white wires form the PS 130-82 Power Cable and the 110VAC plug into the right
side of the terminal strip socket #2
11. Place the red wire from the PS130-28 power cable into the right side of the terminal strip Socket
#3.
12. Place both the black wire from the PS130-28 Power Cable and the black wire coming from the
110VAC fuse box into the right side of the terminal strip in socket #4. This should conclude the wiring for
the junction box. Make sure that each wire is secure. Fasten the top back on the junction box.