7.5 Check protective equipment
7 Commissioning
The test piece interrupts the advance measuring field. The press stroke 
is stopped. The upper tool should not touch the test piece.
 Once the press stroke has stopped, push the 15 mm high section of 
the test piece beneath the upper tool.
The upper tool should not touch the test piece.
Function test using the 35 mm test piece
 Start up the press.
 Position the 35 mm high section of the test piece on top of the lower 
tool.
 Initiate a press stroke.
The test piece interrupts the advance measuring field. The press stroke 
is stopped. The upper tool should not touch the test piece.
7.5.2 Visual inspection
Visual inspection7-Inbetriebnahme_Schutzeinrichtung_pruefen_Sichtpruefung
Check the following on the PSENvip transmitter and receiver
 The condition of the installation and attachment
 Any damage on the housing and lens
 Electrical connections
 Switch on the machine.
 Check the messages on the display.