Installation Manual

Electrical & Electronic Application And Installation Manual
Production Release Version 1.0
Page 95
8.2.2.1 PETU Power Supply Connection
Power supply connections to the PETU are supplied pre-terminated at a 4-
way connector mounted on the side of the PEU. The unit requires fused un-
switched battery connection for power supply to the DEF controller and pump.
Electrical connection requirements and installation schematic are shown
below.
Figure 8.6 PETU Power Supply Connection
Component
Description
Perkins
Part Number
S
upplier Part Number
Quantity
4-way 12-14AWG
Connector
N/A Deutsch DTP06-4S-
E003
1
Connector Wedge
Lock
N/A Deutsch WP-4S 1
Connector and wedge
lock Kit
T400035 N/A N/A
Terminal Socket T400045 AMP 0462-203-12141 4
Table 8.3 PETU Power Connector Part Numbers
Figure 8.7 PETU Power Schematic
8.2.2.2 PETU Communication Connection
All PETU communication connections are supplied pre terminated at a 12-way
connector mounted to the side of the PEU. Communication from the engine
ECM to the PETU controller is provided via a dedicated CAN bus link which
contains proprietary information only. The 12-way connector also provides
the electrical supply signal out to the DEF injector mounted on the IG CEM
module.
Figure 8.8 PETU Communications Connector
1
BATT POWER +
2
BATT POWER +
3
BATT POWER -
4
BATT POWER -
PETU Power Connection
FUSED UNSWITCHED BATTERY +
FUSED UNSWITCHED BATTERY -
10AWG
12AWG
12AWG
12AWG
12AWG
10AWG