11.3.3 Power-up Restoration
The following steps will ensure the PMP equipment will restore back to an operational state with the inter-
ruption of power:
STEP 1. Connect an ATM Test Set to the Sector Physical Port. Place an ATM Port of the
Remote IDU into an ATM mode and the ATM Test Set will generate ATM packets.
STEP 2. Allow the system to stabilize into an operational state and turn the power off to the Sec-
tor Terminal. The ATM Test Set should be displaying bit/packet errors.
STEP 3. Reapply power to the Sector Terminal. After approximately one minutes, the bit/packet
errors displayed on the ATM Test Set should halt.
11.3.4 ATM Connectivity (End-to-End) Test
The following steps will verify end-to-end ATM connection has been established between a Sector and
Remote Terminal:
STEP 1. Provision, with the ATM Test Set, a CBR connection with the appropriate VPI/VCI
between the ATM switch and the Remote IDU.
STEP 2. Place the Remote IDU under test into ATM Loopback.
STEP 3. Reset the ATM Test Set and allow the test to run for 5 minutes.
STEP 4. Verify the equipment can handle the traffic with no cell loss.
STEP 5. Perform tests on all ports.