User Manual

November 1999
4-2 M68333 Rev. A Tel-Link PMP - Sector Terminal Installation & Maintenance Manual
4.2 IDU Installation Preparation
Verify the location selected has the following characteristics:
Identify IDU mounting location as specified in a completed Site Survey Checklist.
Verify the required rack (if used) is installed, secured to the floor, and ready to accept the IDU.
Sufficient space is provided for the installation of the ODU Power Supply.
4.3 Power Preparation
Verify the location selected has the following characteristics:
Verify the correct power source has been provided within close proximity to the IDU location.
Verify the power source is controlled through an appropriately sized circuit breaker or fuse
4.4 IFL Installation Preparation
NOTE: Maximum cable length of 1000 ft (300 meters) between the IDU and ODU.
P-COM recommends the IFL should be Times-Microwave LMR-400 coaxial cable.
Verify the IFL between the ODU and Basic IDU chassis location is present.
Verify a sufficient length of IFL is present at both ends to provide a service loop prior to being
terminated to the equipment.
Terminate each end of the IFL with a Type-N male connector per manufacturers instructions.
Apply liquid electrical sealant to the outdoor connector outer crimp ring to ensure a waterproof
seal between the cable and connector.