Installing the RTU
9
As with all wireless communication devices, the higher the
transmitter is installed, the better the communication will be.
Field Installation
Installing addSWITCH RTUs in the field is a fairly simple process.
You can perform a connectivity check with a LED tool. The LED
tool is shown in Figure 2.
Figure 2. LED Tool
Note: The LED tool is a blind plug to be connected to the POWER
connector.
Follow these steps to install an addSWITCH RTU in the field:
1. Review the installation area and choose the best site.
2. Perform a connectivity check using the LED tool:
a. Insert the LED tool into the POWER connector and wait
up to 10 seconds. If the unit connects to at least one
station (or a base station), it will light up the LED for
about 4 seconds.
b. Keep observing the LED tool and, after another several
seconds, the LED will blink one or more times (the
number of blinks indicates the number of stations it has
contacted).
3. Assemble the rod from the set of poles.
4. Using a hammer, drive the aluminum rod into the ground.
How far you drive the rod into the ground depends on your
application. Put a plastic cap on top of the rod to protect it.
5. Using a ring clamp, fasten the solar panel onto the aluminum
rod. Ensure that the panel is facing south (north if you are
located in the southern hemisphere) and out of the way of the
addSWITCH RTU.