Installation Guide
CONCRETE PAD INSTALL
FIGURE A - Before installing grill island, please review local building code requirements in your
area. It may also necessary to construct a concrete pad to set the unit on. Before construction of the
concrete pad it is necessary to establish Finish Grade height first to ensure the first course of the
unit is buried 4”. Once finished height has been determined construction of the concrete pad can be
completed.
FIGURE B - Sample framework for concrete pad.
FIGURE C - Sample side view of completed concrete pad.
FIGURE B & C - A properly constructed level footing is required to place your bottom unit on. If you
are unfamiliar with soil conditions and the process of pouring a concrete footing, please consult
a professional masonry contractor. Be sure to follow all local building codes before beginning
construction.
4” CONCRETE
PAD
6” GRAVEL
BASE
8" CONCRETE
PYLON
NATIVE SOIL
FROST LINE
WOOD FRAME
8" CONCRETE
PYLON
6" GRAVEL
BASE
WIRE MESH
- 8 -
CARDBOARD
FORM